Substation Scout

Comanche, OK interconnection queue

10 active projects totaling 2,911.3 MW in the SPP queue, plus 7 with terminal status (shown grayed).

10active projects
2,911.3active MW
17total filed
Queue IDProjectkVMWResourceStatus
GEN-2001-011 Not reported n/r 900 Gas Withdrawn
ERAS-2025-024 Not reported 138 744 Gas Active
ERAS-2025-026 Not reported 345 744 Gas Active
GEN-2001-012 Not reported n/r 600 Gas Withdrawn
GEN-2020-087 Not reported 345 500 Solar Active
GEN-2002-016 Not reported n/r 354 Gas Withdrawn
GEN-2018-115 Not reported 345 250 Hybrid Active
GEN-2024-367 Not reported 345 250 Battery Active
GEN-2017-174 Not reported n/r 200 Solar Withdrawn
GEN-2020-075 Not reported 345 200 Battery Withdrawn
GEN-2017-171 Not reported 345 150 Solar Active
GEN-2023-018 Not reported 138 120 Battery Withdrawn
GEN-2008-037 Not reported 138 99 Wind Operational
GEN-2001-026 Not reported 138 74.3 Wind Operational
GEN-2017-172 Not reported 345 50 Solar Active
GEN-2017-173 Not reported 345 50 Solar Active
GEN-2019-027 Not reported 138 40 Gas Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.