Substation Scout

Coal, OK interconnection queue

2 active projects totaling 700 MW in the SPP queue, plus 1 with terminal status (shown grayed).

2active projects
700active MW
3total filed
Queue IDProjectkVMWResourceStatus
GEN-2024-165 Not reported 345 500 Hybrid Active
GEN-2023-038 Not reported 138 200 Solar Active
GEN-2022-110 Not reported 138 150 Battery Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first