Substation Scout

Anderson, KS interconnection queue

0 active projects totaling 0 MW in the SPP queue, plus 7 with terminal status (shown grayed).

0active projects
0active MW
7total filed
Queue IDProjectkVMWResourceStatus
GEN-2023-026 Not reported 345 300 Battery Withdrawn
GEN-2004-011 Not reported n/r 201 Wind Withdrawn
GEN-2005-001 Not reported n/r 201 Wind Withdrawn
GEN-2005-014 Not reported n/r 201 Wind Withdrawn
GEN-2007-022 Not reported n/r 201 Wind Withdrawn
GEN-2016-012 Not reported 345 200 Wind Withdrawn
GEN-2010-050 Not reported n/r 150.4 Wind Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first