Sylvania - Waynesboro Primary Line substation interconnection queue

1 active project totaling 40 MW in the Southern Company queue, plus 2 with terminal status (shown grayed).

3 Southern Company queue filings name Sylvania - Waynesboro Primary Line as the point of interconnection, all in GA.

1active projects
40active MW
3total filed
Queue IDProjectkVMWResourceStatus
IC-766 Not reported 115 107.1 Solar Withdrawn
IC-620 Not reported 115 106.7 Solar Withdrawn
IC-759 Not reported 115 40 Solar Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Southern Company before relying on these figures.