Sandersville #1 - Wadley Primary LIne substation interconnection queue

1 active project totaling 127.5 MW in the Southern Company queue, plus 1 with terminal status (shown grayed).

2 Southern Company queue filings name Sandersville #1 - Wadley Primary LIne as the point of interconnection, all in GA.

1active projects
127.5active MW
2total filed
Queue IDProjectkVMWResourceStatus
IC-1172 Not reported 230 127.5 Solar Active
IC-495 Not reported 230 100 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Southern Company before relying on these figures.