Substation Scout

North Tifton - Stump Creek Line substation interconnection queue

1 active project totaling 200 MW in the Southern Company queue, plus 1 with terminal status (shown grayed).

2 Southern Company queue filings name North Tifton - Stump Creek Line as the point of interconnection, all in Irwin County, GA.

1active projects
200active MW
2total filed
Queue IDProjectkVMWResourceStatus
IC-1094 Not reported 230 200 Solar Active
IC-740 Not reported 115 75 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Southern Company before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first