North Tifton - Pitts Line substation interconnection queue
2 active projects totaling 330.5 MW in the Southern Company queue, plus 7 with terminal status (shown grayed).
9 Southern Company queue filings name North Tifton - Pitts Line as the point of interconnection, all in Turner County, GA.
2active projects
330.5active MW
9total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| IC-794 | Not reported | 230 | 343 | Solar | Withdrawn |
| IC-908 | Not reported | 230 | 220 | Solar | Suspended |
| IC-944 | Not reported | 230 | 210 | Solar | Withdrawn |
| IC-962 | Not reported | 230 | 200 | Hybrid | Withdrawn |
| IC-476 | Not reported | 230 | 170 | Solar | Withdrawn |
| IC-753 | Not reported | 230 | 170 | Solar | Withdrawn |
| IC-640 | Not reported | 230 | 155 | Solar | Withdrawn |
| IC-1074 | Not reported | 230 | 110.5 | Solar | Suspended |
| IC-641 | Not reported | 230 | 110.5 | Solar | Withdrawn |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Southern Company before relying on these figures.