North Camilla - Hopeful Line substation interconnection queue
0 active projects
totaling 0 MW in the Southern Company queue, plus 3 with terminal status (shown grayed).
3 Southern Company queue filings name North Camilla - Hopeful Line as the point of interconnection, all in Mitchell County, GA.
0active projects
0active MW
3total filed
Queue ID
Project
kV
MW
Resource
Status
IC-653
Not reported
46
83.9
Solar
Withdrawn
IC-383
Not reported
46
20
Solar
Withdrawn
IC-545
Not reported
46
20
Solar
Withdrawn
A request with terminal status left the queue as filed.
That is a record of the filing, not evidence of injection capacity at this location.
Confirm deliverability with Southern Company before relying on these figures.