Substation Scout

Homeland - Kettle Creek Primary Line substation interconnection queue

0 active projects totaling 0 MW in the Southern Company queue, plus 2 with terminal status (shown grayed).

2 Southern Company queue filings name Homeland - Kettle Creek Primary Line as the point of interconnection, all in Ware County, GA.

0active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatus
IC-843 Not reported 230 163 Hybrid Withdrawn
IC-728 Not reported 230 124 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Southern Company before relying on these figures.