Substation Scout

Hatch Substation Bus substation interconnection queue

2 active projects totaling 125 MW in the Southern Company queue.

2 Southern Company queue filings name Hatch Substation Bus as the point of interconnection, all in Appling County, GA.

2active projects
125active MW
2total filed
Queue IDProjectkVMWResourceStatus
25-IC-1302 Not reported 500 65 Nuclear Active
25-IC-1301 Not reported 230 60 Nuclear Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Southern Company before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first