Greenville - Pintlala Line substation interconnection queue
2 active projects totaling 138 MW in the Southern Company queue, plus 10 with terminal status (shown grayed).
12 Southern Company queue filings name Greenville - Pintlala Line as the point of interconnection, all in AL.
2active projects
138active MW
12total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| IC-968 | Not reported | 115 | 300 | Solar | Withdrawn |
| IC-1169 | Not reported | 115 | 200 | Hybrid | Withdrawn |
| IC-1182 | Not reported | 115 | 138 | Hybrid | Withdrawn |
| IC-1007 | Not reported | 115 | 80 | Solar | Withdrawn |
| IC-1008 | Not reported | 115 | 80 | Solar | Withdrawn |
| IC-1020 | Not reported | 115 | 80 | Hybrid | Withdrawn |
| IC-1092 | Not reported | 115 | 80 | Hybrid | Withdrawn |
| IC-1093 | Not reported | 115 | 80 | Hybrid | Withdrawn |
| IC-1154 | Not reported | 115 | 80 | Hybrid | Withdrawn |
| IC-711 | Not reported | 115 | 80 | Solar | Withdrawn |
| IC-971 | Not reported | 115 | 80 | Hybrid | Suspended |
| IC-955 | Not reported | 115 | 58 | Hybrid | Suspended |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Southern Company before relying on these figures.
Site Scanner