Eufaula - Fort Mitchell Line substation interconnection queue

1 active project totaling 80 MW in the Southern Company queue, plus 2 with terminal status (shown grayed).

3 Southern Company queue filings name Eufaula - Fort Mitchell Line as the point of interconnection, all in AL.

1active projects
80active MW
3total filed
Queue IDProjectkVMWResourceStatus
IC-1087 Not reported 115 80 Hybrid Suspended
IC-462 Not reported 115 80 Solar Withdrawn
IC-609 Not reported 115 79.5 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Southern Company before relying on these figures.