East Bainbridge - Spring Creek (Black) Line substation interconnection queue
1 active project totaling 78 MW in the Southern Company queue, plus 9 with terminal status (shown grayed).
10 Southern Company queue filings name East Bainbridge - Spring Creek (Black) Line as the point of interconnection, all in GA.
1active projects
78active MW
10total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| IC-677 | Not reported | 115 | 150 | Solar | Withdrawn |
| IC-692 | Not reported | 115 | 130 | Solar | Withdrawn |
| IC-436 | Not reported | 115 | 100 | Solar | Withdrawn |
| IC-1027 | Not reported | 115 | 90 | Hybrid | Withdrawn |
| IC-1115 | Not reported | 115 | 80 | Solar | Withdrawn |
| IC-607 | Not reported | 115 | 80 | Solar | Withdrawn |
| IC-835 | Not reported | 115 | 80 | Hybrid | Withdrawn |
| IC-432 | Not reported | 115 | 78.6 | Solar | Withdrawn |
| IC-1002 | Not reported | 115 | 78 | Solar | Suspended |
| IC-328 | Not reported | 115 | 50 | Solar | Withdrawn |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Southern Company before relying on these figures.