Substation Scout

Cartersville - Pinson LIne substation interconnection queue

1 active project totaling 200 MW in the Southern Company queue, plus 1 with terminal status (shown grayed).

2 Southern Company queue filings name Cartersville - Pinson LIne as the point of interconnection, all in Bartow County, GA.

1active projects
200active MW
2total filed
Queue IDProjectkVMWResourceStatus
IC-868 Not reported 230 200 Solar Active
IC-1095 Not reported 230 50 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Southern Company before relying on these figures.