0 active projects
totaling 0 MW in the Southern Company queue, plus 3 with terminal status (shown grayed).
3 Southern Company queue filings name Branch Substation Substation as the point of interconnection, all in Putnam County, GA.
0active projects
0active MW
3total filed
Queue ID
Project
kV
MW
Resource
Status
IC-242
Not reported
230
1,922
Gas
Withdrawn
IC-241
Not reported
230
961
Gas
Withdrawn
IC-362
Not reported
230
29.7
Solar
Withdrawn
A request with terminal status left the queue as filed.
That is a record of the filing, not evidence of injection capacity at this location.
Confirm deliverability with Southern Company before relying on these figures.
Site Scanner
Before you spend weeks on a site, spend seconds screening it.