Bonaire Primary - Eastman Primary Line substation interconnection queue
2 active projects totaling 240.2 MW in the Southern Company queue, plus 5 with terminal status (shown grayed).
7 Southern Company queue filings name Bonaire Primary - Eastman Primary Line as the point of interconnection, all in GA.
2active projects
240.2active MW
7total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| IC-624 | Not reported | 115 | 120.2 | Solar | Withdrawn |
| IC-768 | Not reported | 115 | 120.2 | Solar | Active |
| 25-IC-1324 | Not reported | 115 | 120 | Solar | Active |
| IC-502 | Not reported | 115 | 68.5 | Solar | Withdrawn |
| IC-889 | Not reported | 115 | 30 | Hybrid | Withdrawn |
| IC-293 | Not reported | 115 | 20 | Solar | Withdrawn |
| IC-626 | Not reported | 115 | 20 | Solar | Withdrawn |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Southern Company before relying on these figures.