Blakely - Webb Line substation interconnection queue
0 active projects totaling 0 MW in the Southern Company queue, plus 2 with terminal status (shown grayed).
0active projects
0active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| IC-578 | Not reported | 115 | 46 | Solar | Withdrawn |
| IC-519 | Not reported | 115 | 45 | Solar | Withdrawn |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Southern Company before relying on these figures.