Bio Substation Bus substation interconnection queue
0 active projects
totaling 0 MW in the Southern Company queue, plus 2 with terminal status (shown grayed).
2 Southern Company queue filings name Bio Substation Bus as the point of interconnection, all in Hart County, GA.
0active projects
0active MW
2total filed
Queue ID
Project
kV
MW
Resource
Status
25-IC-AS
Not reported
230
199
Battery
Withdrawn
IC-622
Not reported
115
150
Solar
Withdrawn
A request with terminal status left the queue as filed.
That is a record of the filing, not evidence of injection capacity at this location.
Confirm deliverability with Southern Company before relying on these figures.