Queue request IC-800 was listed in the Southern Company interconnection queue at the end of 2025 as a 200 MW solar project in Taylor County, GA, according to Berkeley Lab’s queue data file. The filing names Patsiliga Creek Substation Bus as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of June 30, 2023.

Queue IDIC-800
Project nameNot reported
Status (as published)Active
SubstationPatsiliga Creek Substation Bus
Point of interconnectionPatsiliga Creek Substation 230 kV Bus
CountyTaylor
StateGA
Voltage230 kV
Capacity200 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2023-06-30
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Taylor, GA: 19 requests in the Southern Company queue, 7 active totaling 818.6 MW.

Tracked changes

Not tracked. Southern Company rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilitySouthern Company
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Queue date2019-07-26

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first