Substation Scout

Southern Company request IC-616

Southern Company queue ID IC-616

Queue request IC-616 was listed in the Southern Company interconnection queue at the end of 2025 as a 117.5 MW solar project in Pierce County, GA, according to Berkeley Lab’s queue data file. The filing names Offerman Substation Bus as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of November 30, 2020.

Queue IDIC-616
Project nameNot reported
Status (as published)Active
SubstationOfferman Substation Bus
Point of interconnectionOfferman Substation 230 kV Bus
CountyPierce
StateGA
Voltage230 kV
Capacity117.5 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2020-11-30
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Offerman Substation Bus substation: 2 requests in the Southern Company queue, 1 active totaling 117.5 MW.

Queue IDProjectMWResourceStatus
IC-307Not reported20SolarWithdrawn

Pierce, GA: 3 requests in the Southern Company queue, 1 active totaling 117.5 MW.

Tracked changes

Not tracked. Southern Company rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilitySouthern Company
Interconnection serviceERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Queue date2017-03-27

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first