Rincon Solar I (IC-329) was listed in the Southern Company interconnection queue at the end of 2025 as a 15.7 MW solar project in Effingham County, GA, according to Berkeley Lab’s queue data file. Its status as of December 31, 2025 was “Operational”.
| Queue ID | IC-329 |
|---|---|
| Project name | Rincon Solar I |
| Status (as published) | Operational |
| Substation | Not reported |
| Point of interconnection | Not reported |
| County | Effingham |
| State | GA |
| Voltage | Not reported |
| Capacity | 15.7 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Proposed online date | Not reported |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Effingham, GA: 24 requests in the Southern Company queue, 15 active totaling 2,434.7 MW.
Tracked changes
Not tracked. Southern Company rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | Southern Company |
|---|---|
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | IA Executed |
| Study phase (as the queue printed it) | Operational |
| Interconnection agreement date | 2015-02-24 |
| Operational date | 2016-12-16 |