Southern Company queue ID IC-1210

Queue request IC-1210 was listed in the Southern Company interconnection queue at the end of 2025 as a 150 MW battery project in Walker County, AL, according to Berkeley Lab’s queue data file. The filing names Goodsprings Substation Bus as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of June 1, 2026.

Queue IDIC-1210
Project nameNot reported
Status (as published)Active
SubstationGoodsprings Substation Bus
Point of interconnectionGoodsprings Substation 230 kV Bus
CountyWalker
StateAL
Voltage230 kV
Capacity150 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2026-06-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Walker, AL: 10 requests in the Southern Company queue, 1 active totaling 150 MW.

Tracked changes

Not tracked. Southern Company rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilitySouthern Company
Interconnection serviceERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Queue date2023-12-08

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first