Southern Company queue ID IC-1177

BC Smith (IC-1177) was listed in the Southern Company interconnection queue at the end of 2025 as a 547 MW gas project in Effingham County, GA, according to Berkeley Lab’s queue data file. Its status as of December 31, 2025 was “Operational”, with a proposed online date of March 15, 2024.

Queue IDIC-1177
Project nameBC Smith
Status (as published)Operational
SubstationNot reported
Point of interconnectionNot reported
CountyEffingham
StateGA
VoltageNot reported
Capacity547 MW
Resource (as published)Gas
Resource categoryGas (normalized for filtering)
Proposed online date2024-03-15
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Effingham, GA: 24 requests in the Southern Company queue, 15 active totaling 2,434.7 MW.

Tracked changes

Not tracked. Southern Company rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilitySouthern Company
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Operational
Queue date2023-09-27
Operational date2024-06-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first