Substation Scout

Southern Company request IC-1159

Southern Company queue ID IC-1159

Queue request IC-1159 was listed in the Southern Company interconnection queue at the end of 2025 as a 403.1 MW gas project in Shelby County, AL, according to Berkeley Lab’s queue data file. The filing names Gaston SP Substation Bus as its point of interconnection. Its status as of December 31, 2025 was “Suspended”, with a proposed online date of June 1, 2030.

Queue IDIC-1159
Project nameNot reported
Status (as published)Suspended
SubstationGaston SP Substation Bus
Point of interconnectionGaston SP Substation 230 kV Bus
CountyShelby
StateAL
Voltage230 kV
Capacity403.1 MW
Resource (as published)Gas
Resource categoryGas (normalized for filtering)
Proposed online date2030-06-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Gaston SP Substation Bus substation: 2 requests in the Southern Company queue, 2 active totaling 806.2 MW.

Queue IDProjectMWResourceStatus
IC-1160Not reported403.1GasSuspended

Shelby, AL: 7 requests in the Southern Company queue, 2 active totaling 806.2 MW.

Tracked changes

Not tracked. Southern Company rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilitySouthern Company
Interconnection serviceERIS
Project typeGeneration
Queue date2023-08-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.