Substation Scout

Southern Company request IC-1144

Southern Company queue ID IC-1144

Queue request IC-1144 was listed in the Southern Company interconnection queue at the end of 2025 as a 260 MW battery project in Bartow County, GA, according to Berkeley Lab’s queue data file. The filing names Kingston Substation Bus as its point of interconnection. Its status as of December 31, 2025 was “Suspended”, with a proposed online date of May 15, 2028.

Queue IDIC-1144
Project nameNot reported
Status (as published)Suspended
SubstationKingston Substation Bus
Point of interconnectionKingston Substation 230 kV Bus
CountyBartow
StateGA
Voltage230 kV
Capacity260 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2028-05-15
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Kingston Substation Bus substation: 2 requests in the Southern Company queue, 1 active totaling 260 MW.

Queue IDProjectMWResourceStatus
IC-1119Not reported200BatteryWithdrawn

Bartow, GA: 17 requests in the Southern Company queue, 8 active totaling 3,848 MW.

Tracked changes

Not tracked. Southern Company rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilitySouthern Company
Interconnection serviceNRIS
Project typeGeneration
Queue date2023-06-09

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.