Southern Company request IC-1084

Southern Company queue ID IC-1084

Queue request IC-1084 was listed in the Southern Company interconnection queue at the end of 2025 as a 470 MW solar project in Coweta County, GA, according to Berkeley Lab’s queue data file. The filing names Plant Wansley Substation Bus as its point of interconnection. Its status as of December 31, 2025 was “Suspended”, with a proposed online date of August 9, 2027.

Queue IDIC-1084
Project nameNot reported
Status (as published)Suspended
SubstationPlant Wansley Substation Bus
Point of interconnectionPlant Wansley Substation 500 kV Bus
CountyCoweta
StateGA
Voltage500 kV
Capacity470 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2027-08-09
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Plant Wansley Substation Bus substation: 6 requests in the Southern Company queue, 4 active totaling 2,414 MW.

Queue IDProjectMWResourceStatus
IC-1263Not reported722GasActive
IC-1264Not reported722GasActive
IC-1247Not reported500BatteryActive
IC-1261Not reported419GasWithdrawn
IC-1262Not reported419GasWithdrawn

Coweta, GA: 11 requests in the Southern Company queue, 7 active totaling 3,032.1 MW.

Tracked changes

Not tracked. Southern Company rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilitySouthern Company
Interconnection serviceNRIS
Project typeGeneration
Queue date2022-10-26

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first