Substation Scout

Southern Company request IC-1042

Southern Company queue ID IC-1042

Queue request IC-1042 was listed in the Southern Company interconnection queue at the end of 2025 as a 200 MW hybrid project in Rockdale County, GA, according to Berkeley Lab’s queue data file. The filing names Conyers TS as its point of interconnection. Its status as of December 31, 2025 was “Suspended”, with a proposed online date of March 31, 2026.

Queue IDIC-1042
Project nameNot reported
Status (as published)Suspended
SubstationConyers TS
Point of interconnectionConyers 115 kV TS
CountyRockdale
StateGA
Voltage115 kV
Capacity200 MW
Resource (as published)Solar+Battery
Resource categoryHybrid (normalized for filtering)
Proposed online date2026-03-31
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Rockdale, GA: 2 requests in the Southern Company queue, 1 active totaling 200 MW.

Tracked changes

Not tracked. Southern Company rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilitySouthern Company
Interconnection serviceNRIS
Project typeGeneration
Queue date2022-07-11
Components (hybrid)Solar 200 MW + Battery

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first