Southern Company request IC-1036
Southern Company queue ID IC-1036
Queue request IC-1036 was listed in the Southern Company interconnection queue at the end of 2025 as a 80 MW solar project in Montgomery County, AL, according to Berkeley Lab’s queue data file. The filing names Blackbear Solar Farm SS Bus as its point of interconnection. Its status as of December 31, 2025 was “Suspended”, with a proposed online date of January 15, 2027.
| Queue ID | IC-1036 |
|---|---|
| Project name | Not reported |
| Status (as published) | Suspended |
| Substation | Blackbear Solar Farm SS Bus |
| Point of interconnection | Blackbear Solar Farm SS 230 kV Bus |
| County | Montgomery |
| State | AL |
| Voltage | 230 kV |
| Capacity | 80 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Proposed online date | 2027-01-15 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Montgomery, AL: 30 requests in the Southern Company queue, 7 active totaling 1,018.8 MW.
Tracked changes
Not tracked. Southern Company rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | Southern Company |
|---|---|
| Interconnection service | NRIS |
| Project type | Generation |
| Queue date | 2022-05-19 |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.