Substation Scout

Southern Company request 25-IC-1382

Southern Company queue ID 25-IC-1382

Queue request 25-IC-1382 was listed in the Southern Company interconnection queue at the end of 2025 as a 707 MW gas project in Mobile County, AL, according to Berkeley Lab’s queue data file. The filing names Bucks SS as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of June 1, 2031.

Queue ID25-IC-1382
Project nameNot reported
Status (as published)Active
SubstationBucks SS
Point of interconnectionBucks SS 230 kV
CountyMobile
StateAL
Voltage230 kV
Capacity707 MW
Resource (as published)Gas
Resource categoryGas (normalized for filtering)
Proposed online date2031-06-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Mobile, AL: 23 requests in the Southern Company queue, 7 active totaling 2,886 MW.

Tracked changes

Not tracked. Southern Company rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilitySouthern Company
Interconnection serviceERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Cluster Study
Queue date2025-04-17

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.