Queue request 25-IC-1354 was listed in the Southern Company interconnection queue at the end of 2025 as a 91 MW solar project in Dale County, AL, according to Berkeley Lab’s queue data file. The filing names Ewell SS - Pinckard Line as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of July 30, 2029.

Queue ID25-IC-1354
Project nameNot reported
Status (as published)Active
SubstationEwell SS - Pinckard Line
Point of interconnectionEwell SS - Pinckard 115 kV Line
CountyDale
StateAL
Voltage115 kV
Capacity91 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2029-07-30
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Dale, AL: 16 requests in the Southern Company queue, 4 active totaling 361 MW.

Tracked changes

Not tracked. Southern Company rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilitySouthern Company
Interconnection serviceERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Cluster Study
Queue date2025-04-16

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.