Southern Company request 25-IC-1326

Southern Company queue ID 25-IC-1326

Queue request 25-IC-1326 was listed in the Southern Company interconnection queue at the end of 2025 as a 250 MW solar project in Jasper County, GA, according to Berkeley Lab’s queue data file. The filing names Glenwood Springs - Porterdale Primary Line as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of August 1, 2030.

Queue ID25-IC-1326
Project nameNot reported
Status (as published)Active
SubstationGlenwood Springs - Porterdale Primary Line
Point of interconnectionGlenwood Springs - Porterdale Primary 230 kV Line
CountyJasper
StateGA
Voltage230 kV
Capacity250 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2030-08-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Jasper, GA: 4 requests in the Southern Company queue, 2 active totaling 500 MW.

Tracked changes

Not tracked. Southern Company rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilitySouthern Company
Interconnection serviceERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Facility Study
Queue date2025-04-11

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first