Substation Scout

Wilcox, GA interconnection queue

1 active project totaling 150 MW in the Southern Company queue, plus 2 with terminal status (shown grayed).

1active projects
150active MW
3total filed
Queue IDProjectkVMWResourceStatus
IC-1238 Not reported 230 250 Solar Withdrawn
IC-1153 Not reported 230 150 Solar Suspended
IC-512 Not reported 115 68.5 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Southern Company before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first