Substation Scout

Upson, GA interconnection queue

0 active projects totaling 0 MW in the Southern Company queue, plus 6 with terminal status (shown grayed).

0active projects
0active MW
6total filed
Queue IDProjectkVMWResourceStatus
IC-248 Not reported 230 968 Gas Withdrawn
IC-253 Not reported 230 968 Gas Withdrawn
IC-250 Not reported 230 782 Gas Withdrawn
IC-247 Not reported 230 520 Gas Withdrawn
IC-116 Not reported 230 474 Gas Withdrawn
IC-249 Not reported 230 391 Gas Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Southern Company before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first