Substation Scout

Tuscaloosa, AL interconnection queue

0 active projects totaling 0 MW in the Southern Company queue, plus 5 with terminal status (shown grayed).

0active projects
0active MW
5total filed
Queue IDProjectkVMWResourceStatus
IC-043 Not reported 230 622 Gas Withdrawn
IC-118 Not reported n/r 520 Coal Withdrawn
IC-120 Not reported n/r 520 Coal Withdrawn
IC-741 Not reported 115 80 Hybrid Withdrawn
IC-239 Not reported 46 2.3 Other Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Southern Company before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first