Substation Scout

Turner, GA interconnection queue

2 active projects totaling 330.5 MW in the Southern Company queue, plus 9 with terminal status (shown grayed).

2active projects
330.5active MW
11total filed
Queue IDProjectkVMWResourceStatus
IC-794 Not reported 230 343 Solar Withdrawn
IC-908 Not reported 230 220 Solar Suspended
IC-944 Not reported 230 210 Solar Withdrawn
IC-962 Not reported 230 200 Hybrid Withdrawn
IC-476 Not reported 230 170 Solar Withdrawn
IC-753 Not reported 230 170 Solar Withdrawn
IC-640 Not reported 230 155 Solar Withdrawn
IC-1074 Not reported 230 110.5 Solar Suspended
IC-641 Not reported 230 110.5 Solar Withdrawn
IC-642 Not reported 115 45 Solar Withdrawn
IC-919 Not reported 46 20 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Southern Company before relying on these figures.