Substation Scout

Peach, GA interconnection queue

1 active project totaling 10.7 MW in the Southern Company queue, plus 4 with terminal status (shown grayed).

1active projects
10.7active MW
5total filed
Queue IDProjectkVMWResourceStatus
IC-907 Not reported 115 100 Hybrid Withdrawn
IC-564 Not reported 115 49.9 Solar Withdrawn
IC-309 Not reported 115 19.8 Solar Withdrawn
IC-354 Not reported 46 19.4 Solar Withdrawn
IC-659 Fort Valley State Solar n/r 10.7 Solar Operational

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Southern Company before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first