Substation Scout

Miller, GA interconnection queue

0 active projects totaling 0 MW in the Southern Company queue, plus 6 with terminal status (shown grayed).

0active projects
0active MW
6total filed
Queue IDProjectkVMWResourceStatus
IC-911 Not reported 230 220 Solar Withdrawn
IC-701 Not reported 115 199.9 Solar Withdrawn
25-IC-BF Not reported 230 199 Other Withdrawn
IC-835 Not reported 115 80 Hybrid Withdrawn
IC-834 Not reported 115 70 Hybrid Withdrawn
IC-629 Not reported 115 20 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Southern Company before relying on these figures.