Laurens, GA interconnection queue

5 active projects totaling 874 MW in the Southern Company queue, plus 7 with terminal status (shown grayed).

5active projects
874active MW
12total filed
Queue IDProjectkVMWResourceStatus
IC-634 Not reported 230 248.5 Solar Withdrawn
IC-544 Not reported 230 240 Solar Withdrawn
IC-727 Not reported 230 240 Solar Withdrawn
IC-1206 Not reported 230 225 Solar Active
IC-1265 Not reported 230 200 Hybrid Active
25-IC-1342 Not reported 230 199 Solar Active
IC-1044 Not reported 115 150 Solar Active
25-IC-1343 Not reported 230 100 Battery Active
IC-543 Not reported 115 40 Solar Withdrawn
IC-594 Not reported n/r 38 Solar Withdrawn
IC-292 Not reported 115 20 Solar Withdrawn
IC-271 Not reported 46 15 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Southern Company before relying on these figures.