Lamar, GA interconnection queue

1 active project totaling 53 MW in the Southern Company queue, plus 1 with terminal status (shown grayed).

1active projects
53active MW
2total filed
Queue IDProjectkVMWResourceStatus
IC-229 Piedmont Green Power n/r 53 Other Operational
IC-995 Not reported 69 22 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Southern Company before relying on these figures.