Substation Scout

Jefferson, AL interconnection queue

1 active project totaling 707 MW in the Southern Company queue, plus 3 with terminal status (shown grayed).

1active projects
707active MW
4total filed
Queue IDProjectkVMWResourceStatus
IC-666 APC Miller Unit 4 POI n/r 707 Coal Operational
IC-1082 Not reported 230 225 Solar Withdrawn
IC-484 Not reported 115 50 Solar Withdrawn
IC-485 Not reported 115 40 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Southern Company before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first