Substation Scout

Jasper, MS interconnection queue

3 active projects totaling 365 MW in the Southern Company queue, plus 4 with terminal status (shown grayed).

3active projects
365active MW
7total filed
Queue IDProjectkVMWResourceStatus
IC-1205 Not reported 230 200 Hybrid Withdrawn
25-IC-1355 Not reported 230 165 Solar Active
IC-707 Not reported 230 160 Solar Withdrawn
IC-Pachuta Solar Not reported 230 160 Hybrid Withdrawn
IC-1145 Not reported 230 156 Solar Active
IC-1031 Not reported 230 150 Hybrid Withdrawn
IC-1203 Not reported 230 44 Solar Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Southern Company before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first