Jackson, FL interconnection queue
0 active projects totaling 0 MW in the Southern Company queue, plus 9 with terminal status (shown grayed).
0active projects
0active MW
9total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| IC-444 | Not reported | 230 | 295 | Solar | Withdrawn |
| IC-442 | Not reported | 230 | 212.7 | Solar | Withdrawn |
| IC-558 | Not reported | 230 | 74.9 | Solar | Withdrawn |
| IC-658 | Not reported | 115 | 74.9 | Solar | Withdrawn |
| IC-668 | Not reported | 115 | 74.9 | Solar | Withdrawn |
| IC-482 | Not reported | 115 | 74.5 | Solar | Withdrawn |
| IC-621 | Not reported | 115 | 74.5 | Solar | Withdrawn |
| IC-708 | Not reported | 115 | 74.5 | Solar | Withdrawn |
| IC-737 | Not reported | 115 | 50 | Hybrid | Withdrawn |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Southern Company before relying on these figures.