Hancock, MS interconnection queue

1 active project totaling 78.5 MW in the Southern Company queue, plus 3 with terminal status (shown grayed).

1active projects
78.5active MW
4total filed
Queue IDProjectkVMWResourceStatus
IC-475 Not reported 115 78.6 Solar Withdrawn
IC-454 Not reported 115 78.5 Solar Withdrawn
MPCQF-454 MoonShot Solar n/r 78.5 Solar Operational
IC-1022 Not reported 115 74 Hybrid Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Southern Company before relying on these figures.