Elbert, GA interconnection queue

3 active projects totaling 269 MW in the Southern Company queue, plus 1 with terminal status (shown grayed).

3active projects
269active MW
4total filed
Queue IDProjectkVMWResourceStatus
IC-1165 Not reported 230 150 Solar Suspended
25-IC-1372 Not reported 115 79 Solar Active
IC-743 Sonny Solar n/r 40 Solar Operational
IC-761 Not reported 46 40 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Southern Company before relying on these figures.