Substation Scout

Douglas, GA interconnection queue

1 active project totaling 500 MW in the Southern Company queue, plus 3 with terminal status (shown grayed).

1active projects
500active MW
4total filed
Queue IDProjectkVMWResourceStatus
IC-1170 Not reported 500 500 Battery Suspended
25-IC-1325 Not reported 230 250 Battery Withdrawn
IC-819 Not reported 230 200 Battery Withdrawn
IC-820 Not reported 230 100 Battery Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Southern Company before relying on these figures.