Clarke, GA interconnection queue

0 active projects totaling 0 MW in the Southern Company queue, plus 9 with terminal status (shown grayed).

0active projects
0active MW
9total filed
Queue IDProjectkVMWResourceStatus
IC-014 Not reported 115 620 Gas Withdrawn
IC-015 Not reported 230 620 Gas Withdrawn
IC-016 Not reported n/r 620 Gas Withdrawn
IC-077 Not reported 230 564 Gas Withdrawn
IC-131 Not reported 230 564 Gas Withdrawn
IC-034 Not reported 115 185 Gas Withdrawn
IC-035 Not reported 230 185 Gas Withdrawn
IC-1186 Not reported 115 130 Battery Withdrawn
IC-1181 Not reported 115 100 Battery Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Southern Company before relying on these figures.