Brooks, GA interconnection queue

2 active projects totaling 300 MW in the Southern Company queue, plus 5 with terminal status (shown grayed).

2active projects
300active MW
7total filed
Queue IDProjectkVMWResourceStatus
IC-847 Not reported 230 175 Hybrid Withdrawn
IC-1033 Not reported 230 150 Solar Withdrawn
IC-608 Quitman Solar n/r 150 Solar Operational
IC-649 Not reported 230 150 Solar Withdrawn
IC-678 Quitman II n/r 150 Solar Operational
IC-674 Not reported 230 75 Solar Withdrawn
IC-376 Not reported 69 20 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Southern Company before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first