Appling, GA interconnection queue
2 active projects totaling 125 MW in the Southern Company queue, plus 3 with terminal status (shown grayed).
2active projects
125active MW
5total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 25-IC-AX | Not reported | 230 | 250 | Solar | Withdrawn |
| IC-553 | Not reported | 230 | 100 | Solar | Withdrawn |
| IC-633 | Not reported | 230 | 80 | Solar | Withdrawn |
| 25-IC-1302 | Not reported | 500 | 65 | Nuclear | Active |
| 25-IC-1301 | Not reported | 230 | 60 | Nuclear | Active |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Southern Company before relying on these figures.