Substation Scout

Wishek Substation substation interconnection queue

0 active projects totaling 0 MW in the MISO queue, plus 2 with terminal status (shown grayed).

2 MISO queue filings name Wishek Substation as the point of interconnection, all in Mcintosh County, ND.

0active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatus
G624 Not reported 115 150 Wind Withdrawn
J929 Not reported 41.6 25 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →