Substation Scout

White Bluff EHV substation interconnection queue

0 active projects totaling 0 MW in the MISO queue, plus 4 with terminal status (shown grayed).

4 MISO queue filings name White Bluff EHV as the point of interconnection, all in Jefferson County, AR.

0active projects
0active MW
4total filed
Queue IDProjectkVMWResourceStatus
J2515 Not reported 500 300 Solar Withdrawn
J2516 Not reported 500 300 Solar Withdrawn
J2459 Not reported 500 100 Battery Withdrawn
J2460 Not reported 500 100 Battery Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first